Plan Sourcing Strategy
Governance's second Planning process — full ITTO (Inputs, Tools & Techniques, Outputs) detail for Plan Sourcing Strategy itself, plus its two nested sub-topics (the 10 Procurement Steps and the 4 Contract Types), reference illustrations, the PMP Mindset behind it all, and a 120-question practice quiz across five sections.
Each stepper item represents an entire focus area, not a single step — Planning alone has 19 processes across 7 domains, so it will take several steps (7, 8, 9…) to finish it. The stepper flips to "done" only once every process in that column has a finished page.
| Domain | Planning Process(es) | Status |
|---|---|---|
| Governance | Integrate & Align Project Plans | ✅ Step 6 |
| Governance | Plan Sourcing Strategy (incl. Procurement Steps, Contract Types) | ✅ Step 7 (this page) |
| Scope | Plan Scope Management, Elicit and Analyze Requirements, Define Scope, Develop Scope Structure | ⬜ upcoming |
| Schedule | Plan Schedule Management, Develop Schedule | ⬜ upcoming |
| Finance | Plan Financial Management, Estimate Costs, Develop Budget | ⬜ upcoming |
| Stakeholders | Plan Stakeholder Engagement, Plan Communications Management | ⬜ upcoming |
| Resources | Plan Resource Management, Estimate Resources | ⬜ upcoming |
| Risk | Plan Risk Management, Identify Risks, Perform Risk Analysis, Plan Risk Responses | ⬜ upcoming |
Governance Plan Sourcing Strategy — Definition
Reference illustration: the whole idea in one picture — decide make (in-house) vs. buy (outsource), set the vendor criteria, and document it all in a Sourcing Strategy Plan — done early in Planning.
- Plan Sourcing Strategy is one process out of Planning's 19 — the second cell in the Governance row, right after Integrate & Align Project Plans.
- Definition: the process of determining how the project will obtain the goods, services, and resources needed to deliver the project's objectives.
- Decides what work will be done internally (make) versus what will be outsourced to external sellers (buy).
- Establishes the source-selection criteria the project will use to evaluate and choose vendors.
- Documents the overall sourcing approach in a sourcing strategy plan that informs subsequent procurement planning.
- Performed early in Planning so that schedule, cost, and resource plans can reflect the make-vs-buy decision.
Performance Domain: Governance · Focus Area: Planning — per the PMBOK 8th Edition Process Chart (see the reference table below). This is process 2 of 19 in Planning, and its two sub-topics — Procurement Steps and Contract Types — are covered later on this same page.
The important PMP mindset is that procurement is not just a purchasing task — it is a project decision involving scope, cost, schedule, resources, risk, quality, and stakeholders all at once.
Governance Plan Sourcing Strategy — Inputs
Reference illustration: the five input categories feeding Plan Sourcing Strategy — the Project Charter, six subsidiary management plans, eight project documents, Enterprise Environmental Factors, and Organizational Process Assets.
- High-level project description, key deliverables, and constraints that influence sourcing decisions.
- Identifies the project sponsor and the PM's authority to commit to vendor agreements.
- Scope management plan, Quality management plan, Scope baseline.
- Schedule management plan, Financial management plan, Resource management plan.
- Milestone list, Requirements documentation, Requirements traceability matrix, Quality metrics.
- Resource requirements, Project team assignments, Risk register, Stakeholder register.
- Marketplace conditions, supplier performance data, regulatory requirements, contracting policies.
- Pre-approved vendors list, prior contracts, lessons learned from prior procurements, standard templates used to build the sourcing plan.
The risk register is particularly important because sourcing decisions can create or reduce risks — for example, dependence on a single supplier. The stakeholder register identifies people such as procurement, legal, finance, or business stakeholders who may influence the decision.
Governance Plan Sourcing Strategy — Tools & Techniques
Reference illustration: the five tools used to find the best sourcing approach — expert judgement, market research, make-or-buy analysis (with its cost/capability/capacity/schedule/risk/strategic-value checklist), source selection analysis, and document analysis.
- Expert judgement — input from individuals with specialized knowledge in procurement, contracting, the relevant industry, and regulatory requirements.
- Market research — examination of industry and specific vendor capabilities to determine what is available, at what cost, and under what terms; includes trade publications, supplier conferences, and online reviews.
Make-or-buy analysis
The central question: "Should we MAKE it ourselves, or BUY it from an external seller?" PMP questions rarely expect the decision to rest on price alone.
- Can we do it, and can we do it economically?
- Do we have the bandwidth, and can we hit the dates?
- What's the risk exposure, and is this work strategically core to keep in-house?
Source selection analysis
Reviews methods used to evaluate and select sellers — the criteria might emphasize:
- Lowest price wins, for straightforward, well-defined work.
- Only pre-qualified sellers are considered.
- Best technical/quality proposal wins.
- Best proposal within a set budget, or the best overall combination of cost and quality.
- Document analysis — reviews existing documents (charter, requirements, prior contracts) to extract information that informs the sourcing approach.
Governance Plan Sourcing Strategy — Outputs
Reference illustration: the two outputs of Plan Sourcing Strategy — the Procurement Management Plan and the Sourcing Strategy Plan, both components of the overall PM Plan.
- Component of the PM plan describing how the team will acquire goods and services from outside the performing organization.
- Includes the type of bidding (international, national, local) and how procurements will be managed.
- Defines what work will be insourced vs. outsourced, with rationale tied to value, schedule, risk, and cost.
- Documents source-selection criteria and, where applicable, the contract-type approach (see Contract Types below).
- Tailored to the project — can be formal or informal, detailed or high-level.
The result is a sourcing strategy that documents the insource/outsource decisions, rationale, source-selection criteria, and — where applicable — the procurement and contract approach. It should be tailored to the project rather than unnecessarily formal or complicated.
Governance Procurement Steps (sub-topic of Plan Sourcing Strategy)
Reference illustration: the 10 practical procurement steps, from identifying the need through to closing the procurement.
Once a sourcing strategy is set, these are the practical steps a PM works through with each vendor. Think of this as moving from "What do we need?" to "Who should provide it?" to "Are they delivering what we agreed?"
- Identify procurement needs — determine what goods, services, or results are needed from outside sources; perform a make-or-buy analysis.
- Create procurement strategy — decide the best delivery method, contract type (see Contract Types below), and procurement phases.
- Prepare procurement documents — SOW (Statement of Work), RFI (Request for Information), RFP (Request for Proposal), RFQ (Request for Quote).
- Advertise the opportunity — let qualified sellers know about the work.
- Hold a bidder conference — answer vendor questions and make sure everyone receives the same information.
- Receive proposals and quotes — sellers submit their responses based on the bid documents.
- Evaluate sellers — compare vendors based on cost, quality, experience, technical ability, delivery date, and other criteria.
- Select seller & negotiate contract — choose the best vendor and agree on cost, schedule, scope, payment terms, and responsibilities (contract type finalized here).
- Monitor contract performance — make sure the seller delivers the work on time, within budget, and according to the contract.
- Close procurement — confirm all work is completed, obligations are fulfilled, and there are no outstanding issues.
SOW, RFI, RFP, and RFQ all communicate the opportunity and requirements to potential sellers. During a bidder conference, the project team clarifies questions and ensures prospective sellers receive consistent information.
Governance Contract Types (sub-topic of Procurement Steps — decided at Steps 2 & 8)
Reference illustration: the four contract types side by side.
A major PMP concept: the contract type determines how financial and performance risk is shared between buyer and seller. Project managers must understand both sides — the goal is a win-win agreement.
- Price agreed upfront for a clearly defined scope.
- Buyer gets price certainty; seller carries more cost risk.
- Best when scope is well understood.
- Buyer reimburses allowable actual costs plus an agreed fee or profit.
- Useful when scope is uncertain or evolving; places more cost risk on the buyer.
- Payment is based primarily on labor time and materials used.
- Flexible when the exact amount of work is hard to define; buyer must monitor expenditure carefully.
- Common in consulting, IT support, and maintenance.
- Buyer and seller establish a target cost and agree how savings or overruns are shared.
- Creates shared financial incentives; useful for large or complex work.
The goal is not simply to get the cheapest supplier. The goal is the best value and risk arrangement for the project, while creating a fair agreement that protects both buyer and seller and supports successful project delivery.
The PMP Mindset
Make deliberate make-or-buy and supplier decisions before procurement begins, considering the full project picture — right sourcing builds stronger projects.
Plan Sourcing Strategy is about making deliberate "make-or-buy" and supplier decisions before procurement begins. The project manager determines what goods, services, or resources are needed, what should be performed internally versus obtained from external sellers, how sellers will be evaluated, and what overall sourcing approach will best support the project's objectives. The important PMP mindset is that procurement is not simply "buying something" — it is a project decision involving scope, cost, schedule, resources, risk, quality, and stakeholders.
Start with the complete project picture
The bigger the picture, the better the decisions — understand the full context before making sourcing decisions.
The Project Charter establishes the high-level context: what the project is trying to achieve, its major deliverables and constraints, and the authority of the project manager and sponsor.
The project manager then looks across the Project Management Plan and project documents. Scope and requirements tell us what may need to be procured; quality requirements tell us how good it must be; schedule and milestones tell us when it must be delivered; financial information establishes cost considerations; and resource information shows whether the organization has the people, skills, materials, or equipment to perform the work internally.
The risk register is particularly important because sourcing decisions can create or reduce risks—for example, dependence on a single supplier. The stakeholder register identifies people such as procurement, legal, finance, or business stakeholders who may influence the decision.
Finally, the project manager considers the external and organizational context. EEF includes marketplace conditions, supplier capabilities, regulations, and contracting policies. OPA provides organizational knowledge such as approved suppliers, previous contracts, templates, and lessons learned.
Then make the sourcing decision
It's not just about price — it's about the bigger picture. Use the right tools, consider all factors, and choose the best approach.
The project manager uses expert judgment, market research, make-or-buy analysis, source-selection analysis, and document analysis to determine the best approach.
The central question is: "Should we MAKE it ourselves, or BUY it from an external seller?"
But PMP questions rarely expect the decision to be based on price alone. Consider cost, capability, capacity, schedule, quality, risk, strategic value, and the organization's ability to perform the work.
If the decision is to buy, the project manager must also decide how sellers will be evaluated. Source-selection criteria might emphasize least cost, qualifications, quality, fixed budget, or overall best value depending on the project.
The result is a sourcing strategy that documents the insource/outsource decisions, rationale, source-selection criteria, and—where applicable—the procurement and contract approach. The strategy should be tailored to the project rather than unnecessarily formal or complicated.
Procurement then becomes a structured journey
Right process. Right suppliers. Brighter projects. From "what do we need?" to "who should provide it?" to "are they delivering what we agreed?"
Once the strategy is established, the practical procurement process follows a logical sequence: 1. Identify needs → 2. Create procurement strategy → 3. Prepare documents → 4. Advertise → 5. Hold bidder conference → 6. Receive proposals/quotes → 7. Evaluate sellers → 8. Select & negotiate → 9. Monitor performance → 10. Close procurement.
Think of this as moving from "What do we need?" to "Who should provide it?" to "Are they delivering what we agreed?"
Procurement documents such as the SOW, RFI, RFP, and RFQ communicate the opportunity and requirements to potential sellers. During a bidder conference, the project team clarifies questions and ensures that prospective sellers receive consistent information. Sellers then submit proposals or quotes, which are evaluated against the established criteria.
The selected seller and buyer negotiate the contract, including scope, cost, schedule, payment terms, responsibilities, and applicable contract type. Once the contract is active, procurement does not end: the project manager must monitor performance against the agreement and ultimately verify completion and close outstanding obligations.
Contract type = risk allocation
Same goal, different paths — the contract type determines how financial and performance risk is shared between buyer and seller.
A major PMP concept is that the contract type determines how financial and performance risk is shared between buyer and seller.
Fixed Price: The price is agreed for a clearly defined scope. The buyer gains greater price certainty, while the seller carries more cost risk if it underestimates its costs. Therefore, fixed price is attractive when the scope is well understood.
Cost Reimbursable: The buyer reimburses allowable actual costs plus an agreed fee or profit. This is useful when the scope is uncertain or evolving, but it places more cost risk on the buyer.
Time & Material: Payment is based primarily on labor time and materials used. It provides flexibility when the exact amount of work is difficult to define, but the buyer must monitor expenditure carefully. It is commonly encountered in consulting, IT support, and maintenance work.
Target Cost: Buyer and seller establish a target cost and agree how savings or overruns will be shared. This creates shared financial incentives and can encourage efficiency, making it useful for complex work where both parties benefit from controlling costs.
The PMP exam shortcut
Six common question types — recognize the question, think of the right answer. Different questions, same key concepts — that's the PMP mindset.
When a question asks "Should we perform this work ourselves or obtain it externally?" → think Make-or-Buy Analysis.
When it asks "What is available in the marketplace?" → think Market Research.
When it asks "How will we compare vendors?" → think Source-Selection Criteria/Analysis.
When it asks "How will the organization acquire external goods or services?" → think Procurement Management Plan.
When it asks "What work is in-house versus outsourced, and why?" → think Sourcing Strategy.
When it asks "Who carries the cost risk?" → think Contract Type.
Don't choose a vendor or contract in isolation — look at the bigger picture, and remember the full PMP sequence.
Do not choose a vendor or contract in isolation. Choose the sourcing approach that best aligns scope, quality, schedule, cost, resources, risk, and stakeholder needs. The goal is not simply to get the cheapest supplier. The goal is the best value and risk arrangement for the project, while creating a fair agreement that protects both buyer and seller and supports successful project delivery.
NEED → MAKE OR BUY → SOURCING STRATEGY → PROCUREMENT → EVALUATE → CONTRACT → MONITOR → CLOSE
Reference The 40-Process Chart — PMBOK 8th Edition
Source: printed handout, "PMBOK 8th Edition Process Chart — Andrew Ramdayal, PMP Exam Prep Course," Technical Institute of America. This chart is being built one focus area at a time as each step's notes are transcribed — it now shows the completed Initiating column plus the first two cells of Planning; the rest of Planning, Executing, Monitoring & Controlling, and Closing will be filled in as those steps are covered.
| Performance Domain | Initiating | Planning |
|---|---|---|
| Governance | Initiate Project or Phase | Integrate & Align Project Plans; Plan Sourcing Strategy |
| Scope | — | — |
| Schedule | — | — |
| Finance | — | — |
| Stakeholders | Identify Stakeholders | — |
| Resources | — | — |
| Risk | — | — |
Recall Recall Quiz
Straight recall — Plan Sourcing Strategy's own ITTO, plus facts about the 10 Procurement Steps and the 4 Contract Types.
Scenario Case Study Quiz
Short, standalone situational questions spanning all three sub-topics: Plan Sourcing Strategy's own inputs/tools, the Procurement Steps, and the Contract Types.
New Format Long Case Studies
Matches the newer PMI exam format: one longer scenario, several linked questions. 5 case studies, 6 questions each, starring famous Hindi film lyricists of the 1950s/60s golden era — Sahir Ludhianvi, Shailendra, Majrooh Sultanpuri, Hasrat Jaipuri, and Kaifi Azmi.
Advanced Planning Focus Area Mix: Step 6 + Step 7
Questions blending Integrate & Align Project Plans and Plan Sourcing Strategy — shared inputs, shared tools, how sourcing outputs roll up into the integrated plan, and the Governance-domain relationship between the two processes.
Mixed Bag Mixed Bag, Steps 1–6
A broader integrative review of everything covered before this step, introducing three new question formats beyond standard multiple-choice: fill-in-the-blank, match-the-following (shuffled options), and multiple-response ("select all that apply").